[Hps] Run Plan for the next week

Jaros, John A. john at slac.stanford.edu
Fri Mar 20 16:59:02 EDT 2015


Dear HPS,

We haven't had beam since shutting down on Monday, but the machine is presently starting to deliver beam to Hall A
with the new RF separator. Once that is operational, they'll attempt to deliver beam to Hall D. If that works, they'll move on to Hall B. 
We hope for beam later tonight.

If they are not successful with Hall D,  and there are concerns that the RF separator will work, they will go to magnetic extraction for both Halls A and B for this weekend.  So in either case, Hall B should be getting beam, hopefully beginning during Saturday owl shift.  We have cancelled the today's day and swing shifts. The March 21 owl shift, which begins tonight at midnight, is on. 

Longer term, HPS will be running over the weekend until Tuesday morning, March 24, at 6AM. We'll begin again on Thursday owl, March 26 and run until Monday, March 30, at 6 AM.  We expect to cancel Tuesday, March 24, day and swing shifts, and Wednesday, March 25, owl, day and swing shifts. 

This block of time, and some luck with machine performance, should get us a good start on commissioning HPS.

Sincerely,

John
HPS RC




 

-----Original Message-----
From: Stepan Stepanyan [mailto:stepanya at jlab.org] 
Sent: Thursday, March 19, 2015 3:20 PM
To: Dave Kashy
Cc: Volker Burkert; Doug Tilles; Cesar Luongo; Glenn Young; Orlando Pastor; Jaros, John A.
Subject: Re: schedule for the torus

Hello Dave,

Thanks for the update. We will follow that plan. Run till 6am on Tuesday, March 24.
Go to restricted access at 6am on Tuesday and stay in restricted access at least to owl on Wednesday, March 25. Then run till 6am on Monday, March 30.

Regards, Stepan

On 3/19/15 4:58 PM, Dave Kashy wrote:
> Hi Stepan,
> We are now planning on shipping the coil to Hall B on Tuesday.
> There is no pressing work that must be done on Monday so plan on taking beam.
> If the weather is not good Tuesday then we will send it Wednesday.
> The forecast for both Tuesday and Wednesday looks promising so we should not be held up by weather.
>
> After we get the coil down there we will likely set the first coil to 30 degrees in preparation for installing the beams and second coil.
> Beams will be a while in coming so there may be another nice "long" run time. I'll give you an update when I can, but likely you will be able to run Wednesday 3/25 through Sunday 3/29.
>
> Dave
>
>
>
> ----- Original Message -----
> From: "Stepan Stepanyan" <stepanya at jlab.org>
> To: "kashy" <kashy at jlab.org>
> Cc: "Volker Burkert" <burkert at jlab.org>
> Sent: Thursday, March 19, 2015 10:16:50 AM
> Subject: schedule for the torus
>
> Hello Dave,
>
> Can you please update on the schedule for torus work in the hall.
> I am mainly interested at this point if you need the hall on Monday, 
> March 23. Machine has planned down on Tuesday, and if do not need hall 
> on Monday we could run and get to restricted access at 7am on Tuesday.
>
> Thanks, Stepan