> Here is what the next couple months are looking like:
>
> Finish 1X dump shielding, instrumentation, and cooling water connections
> Joe & Kevin will bring out SS 1/4” tubing beyond SEG blocks & Installation crew will tie into the dump water skid
>
> Shield blocks will be removed Sept 5, blocks to be reinstalled in late Sept/early Oct.
>
> LCLS-II cryomodules will be warmed up ~ week of Sept. 10
> Mike/Curt are discussing with SLAC additional tests on CMs/LLRF since run is extended
>
> The drive laser parts are due in the next couple weeks - we would like to do a CW run to the 1G dump prior to CHL reconfiguration ~Last week of Aug?
>
> Readiness review in Sept? EH&S chapter still in review
>
> 1kWatt isotope run in Oct?
>
> No more LCLS-II CMs till HE (high energy upgrade) ~ 20 months
>
> Kevin
>
> _______________________________________________
> Lerftest mailing list
> Lerftest at jlab.org
> https://mailman.jlab.org/mailman/listinfo/lerftest
More information about the Isotope-prod
mailing list