[Isotope-prod] Gradient recovery or the LERF
Kevin Jordan
jordan at jlab.org
Thu Jan 30 11:12:46 EST 2020
Dear All,
Last night we were able to commission the “1X” isotope area beamline. However, we have insufficient gradient to proceed with the Gallium irradiation. Only 2 of the 8 cavities were able to be used, the others had frozen tuners.
In order to recover these cavities we need a 300k cryocycle, I would propose to do this over the next ~10 days. Additionally we would like a 30/40k cycle done on the 1/4 CM to clean up the leaking helium gas into beamline vacuum.
Next weeks irradiation is canceled, the following week SLAC folks are scheduled to be here for LLRF development. I would propose we reschedule the irradiation run beginning Tuesday February 17.
I would like to discuss options after the 0800 meeting tomorrow
Best regards,
Kevin