Below are the activities for the next two weeks, next week is firm the following week details/directions for Ops need to be firmed up... White board is being updated daily
http://lerfboard.acc.jlab.org/

Kevin

Friday 9/4
Recesiate gun (Carlos)
Install top hats (Larry F)
Tune LCLS-II cavities (Mike D)

Tuesday 9/8
Microphonics studies on LCLS-II (SRF/Peter O)
HCO - All groups

Wednesday 9/9
Microphonics studies on LCLS-II (SRF/Peter O)
HCO - All Groups

Thursday 9/10
MPS Checkout (SSG)
HCO
Turn on ALL RF & DC power
Soak RF

Friday 9/11
Soak RF all day

Monday 9/14
Restore beam to 1X (Ops support)

Tuesday 9/15
Restore beam to 1X (Ops support)

Wednesday 9/16
Isotope irradiation

Thursday 9/17
Complete Isotope irradiation

Friday 9/18
Remove shield blocks







Sent from my iPad
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20200904/8b5fc74e/attachment-0001.html>


More information about the Isotope-prod mailing list