[Isotope-prod] LERF LCLS-II Schedule

Naeem Huque huque at jlab.org
Wed Sep 9 13:54:12 EDT 2020


Hello Everyone,

I have a tentative schedule for getting the LCLS-II CM out of the LERF over the next few weeks. Some of the dates may be out-of-date, and others may find conflicts; I hope to get any such feedback from this email chain. Please also feel free to pass it along to anyone that may be relevant.

Friday, September 11th
LCLS-II supply u-tubes are pulled (Cryo)
CM warm-up begins (SRF)

Saturday, September 12th
CM warm-up (SRF)

Sunday, September 13th
CM warm-up (SRF)

Monday, September 14th
CM warm-up complete (SRF)
Isotope Run prep

Tuesday - Thursday
Isotope run (LERF)

Friday, September 18th
Concrete Blocks are pulled from LERF entrance (Neil Wilson)

Monday, September 21st
CM Bellows are re-positioned (Neil Wilson)
Partial CM disassembly, excluding cryo lines (SRF)

Tuesday, September 22nd
CM cables pulled (Larry Farrish)
Partial CM disassembly, excluding cryo lines (SRF)

Wednesday, September 23rd
Return U-tube is pulled (cryo)
Remaining CM disassembly (SRF)

Thursday, September 24th or Friday, September 25th
CM is pulled from the LERF vault (Neil Wilson/SRF)

Please let me know if there are any issues or comments

Thanks,
Naeem

Naeem Huque
Staff Engineer
Superconducting Radiofrequency (SRF)
Jefferson Lab
12000 Jefferson Ave
Newport News
VA, 23606
Cell: 217-721-5422
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20200909/ea53a57a/attachment.html>


More information about the Isotope-prod mailing list