[Isotope-prod] LERF LCLS-II Schedule
Naeem Huque
huque at jlab.org
Wed Sep 9 15:09:18 EDT 2020
All,
After getting the first round of input, the schedule has been changed to the following:
Friday, September 11th
LCLS-II supply u-tubes are pulled (Cryo)
CM warm-up begins (SRF)
Saturday, September 12th
CM warm-up (SRF)
Sunday, September 13th
CM warm-up (SRF)
Monday, September 14th
CM warm-up complete (SRF)
Isotope Run prep
Tuesday - Thursday
Isotope run (LERF)
Friday, September 18th
Concrete Blocks are pulled from LERF entrance (Neil Wilson)
Monday, September 21st
CM Bellows are re-positioned (Neil Wilson)
Partial CM disassembly, excluding cryo lines (SRF)
Tuesday, September 22nd
CM cables pulled (Larry Farrish)
Partial CM disassembly, excluding cryo lines (SRF)
Wednesday, September 23rd
Partial CM disassembly, excluding cryo lines (SRF)
Thursday, September 24th
Return U-tube is pulled (cryo)
Friday, September 25th
Complete CM disassembly
Monday, September 28th
Remove CM from LERF vault
Thanks,
Naeem
________________________________
From: Naeem Huque
Sent: Wednesday, September 9, 2020 1:54 PM
To: isotope-prod at jlab.org <isotope-prod at jlab.org>; Kevin Jordan <jordan at jlab.org>; Steve Benson <felman at jlab.org>; Jonathan Creel <creel at jlab.org>; Joe Wilson <jwilson at jlab.org>; Neil Wilson <wilsonn at jlab.org>; John Fischer <fischer at jlab.org>; Brian Mastracci <brianm at jlab.org>; David Savransky <dsavr at jlab.org>; Matt Weaks <weaksmc at jlab.org>; Justin Kent <jtkent at jlab.org>; Anna Shabalina Solopova <shabalin at jlab.org>; Michael Drury <drury at jlab.org>; Larry Farrish <lfarrish at jlab.org>
Cc: Joe Preble <preble at jlab.org>; Mike Spata <spata at jlab.org>; Tony Reilly <areilly at jlab.org>
Subject: LERF LCLS-II Schedule
Hello Everyone,
I have a tentative schedule for getting the LCLS-II CM out of the LERF over the next few weeks. Some of the dates may be out-of-date, and others may find conflicts; I hope to get any such feedback from this email chain. Please also feel free to pass it along to anyone that may be relevant.
Friday, September 11th
LCLS-II supply u-tubes are pulled (Cryo)
CM warm-up begins (SRF)
Saturday, September 12th
CM warm-up (SRF)
Sunday, September 13th
CM warm-up (SRF)
Monday, September 14th
CM warm-up complete (SRF)
Isotope Run prep
Tuesday - Thursday
Isotope run (LERF)
Friday, September 18th
Concrete Blocks are pulled from LERF entrance (Neil Wilson)
Monday, September 21st
CM Bellows are re-positioned (Neil Wilson)
Partial CM disassembly, excluding cryo lines (SRF)
Tuesday, September 22nd
CM cables pulled (Larry Farrish)
Partial CM disassembly, excluding cryo lines (SRF)
Wednesday, September 23rd
Return U-tube is pulled (cryo)
Remaining CM disassembly (SRF)
Thursday, September 24th or Friday, September 25th
CM is pulled from the LERF vault (Neil Wilson/SRF)
Please let me know if there are any issues or comments
Thanks,
Naeem
Naeem Huque
Staff Engineer
Superconducting Radiofrequency (SRF)
Jefferson Lab
12000 Jefferson Ave
Newport News
VA, 23606
Cell: 217-721-5422
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20200909/87d108d4/attachment.html>
More information about the Isotope-prod
mailing list