[Isotope-prod] No 11:00 meeting
John Hogan
hogan at jlab.org
Wed Nov 10 08:48:33 EST 2021
Camille & Kevin,
We are still expecting to begin HE CM testing in December 2022. We would like to get the SSA's checked out in advance to account for any potential unplanned activities required to properly run and test.
Thanks,
John
From: Camille Ginsburg <ginsburg at jlab.org>
Sent: Wednesday, November 10, 2021 8:20 AM
To: Kevin Jordan <jordan at jlab.org>; LCLS II @ LERF <lerftest at jlab.org>; isotope-prod at jlab.org
Cc: John Hogan <hogan at jlab.org>; Haipeng Wang <haipeng at jlab.org>
Subject: Re: No 11:00 meeting
Dear Colleagues,
John Hogan's email from 10/22 states:
FYI: The current schedule has the start of the first production cryomodule testing in the LERF beginning December 2022.
What is our best estimate?
Best wishes,
Camille
________________________________
From: Isotope-prod <isotope-prod-bounces at jlab.org<mailto:isotope-prod-bounces at jlab.org>> on behalf of Kevin Jordan <jordan at jlab.org<mailto:jordan at jlab.org>>
Sent: Wednesday, November 10, 2021 8:08 AM
To: LCLS II @ LERF <lerftest at jlab.org<mailto:lerftest at jlab.org>>; isotope-prod at jlab.org<mailto:isotope-prod at jlab.org> <isotope-prod at jlab.org<mailto:isotope-prod at jlab.org>>
Cc: John Hogan <hogan at jlab.org<mailto:hogan at jlab.org>>; Haipeng Wang <haipeng at jlab.org<mailto:haipeng at jlab.org>>
Subject: [Isotope-prod] No 11:00 meeting
LERF Update:
The instrument air went off line last week; an oil separator failed an one of the two compressors shut down - there is limited AC power at the compressor location so the backup compressor had to be manually started. The primary compressor should be repaired today. Bubba & I will reconnect the GTS to the instrument air system this AM.
The OSPs for commissioning & operating the Magnetron transmitter are nearing completion. My goal in to have the transmitter powered up before Thanksgiving.
There was a meeting held with SLAC about modifications to the LCLS-II HE solid state amplifiers. These new 7kwatt SSAs have a phase rotation circuit so there is a question if the phasing is correct - the plan is to power each one up to check the phases if they are all OK then (.), if they are all wrong then we'll make a single change at the breaker panel feed. Other than IP address settings it was unclear if there were any other changes to be made. SLAC will send documentation regarding SSA commissioning in a week of so. The first HE cryomodule test will be ~September.
Best regards,
Kevin
_______________________________________________
Isotope-prod mailing list
Isotope-prod at jlab.org<mailto:Isotope-prod at jlab.org>
https://mailman.jlab.org/mailman/listinfo/isotope-prod
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/isotope-prod/attachments/20211110/8d081541/attachment-0001.html>
More information about the Isotope-prod
mailing list