[Lcls-ii] LCLS-II Responsibilities
Christine Fragapane
chummel at jlab.org
Wed Jul 17 14:33:13 EDT 2019
Sent on behalf of Joe Preble:
Dear All,
Naeem Huque has taken over responsibility as LCLS-II CM Project Engineer starting 7/15. He will focus on ensuring that the assembly, testing and shipping efforts remain on track as CM production continues toward completion in March of 2020. Please support Naeem in his new role as he takes us to the completion of the LCLS-II Project.
Naeem takes over for Katherine Wilson, who has done a very good job providing leadership for procurements, especially high-performing world-class cavities, and helping guide the CM assembly efforts. We would like to take this opportunity to sincerely thank Katherine for all of her contributions for LCLS-II up to now. Katherine will continue to ensure that key components such as cavities and beamline bellows are available for the remainder of the CM production efforts. Katherine will stay busy with CAM roles in both SNS PPU and LCLS-II HE. I wish her well in these new roles.
Joe Preble
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/lcls-ii/attachments/20190717/be9145a6/attachment.html>
More information about the LCLS-II
mailing list