Hi Neil,
As you can see in the photo the panel at the base of the LLRF rack will be removed, this will open a hole starting at 8” above the floor. The heliax cables will have to swing gently up off the floor, through the grating and into this gap. I will have new panels made with a mouse hole cut out for the cables to enter the rack.

Thanks
Kevin




Sent from my iPad

> On Mar 9, 2018, at 6:49 AM, Neil Wilson <wilsonn at jlab.org> wrote:
> 
> Hi All,
> We are in the process of cutting & prepping the materials to install the raised floor. However before we can start actual installation we need the area cleared of all the misc. pieces of equipment, cables, extension cords, etc. I don't know who owns all of this but please address it as soon as practical. 
> Thanks
> n
> _______________________________________________
> Lerftest mailing list
> Lerftest at jlab.org
> https://mailman.jlab.org/mailman/listinfo/lerftest
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/lerftest/attachments/20180309/6fe09eeb/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image1.jpeg
Type: image/jpeg
Size: 357438 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/lerftest/attachments/20180309/6fe09eeb/attachment-0001.jpeg>


More information about the Lerftest mailing list