[Lerftest] Fwd: Draft schedule
Kevin Jordan
jordan at jlab.org
Thu Oct 4 07:36:54 EDT 2018
>
> Attached is the draft time line of cryogenic & accelerator ops
> Activities for the LERF over the next year include:
> 1. Test LCLS-II cryomodules
> Cryo-Can is “last” item to be delivered - ETA ~ 2 (3) weeks, it then needs to be piped in ~ 2 to 3 more weeks
> 2. Re-establish beam for isotopes project (~ 40 MeV ~ 1 milliamp CW)
> 3. Degaussing studies of C20/50
> This includes thermal cycles
>
> I am working on a more detailed activity list, it will be sent shortly
> Kevin
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/lerftest/attachments/20181004/de4904b4/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: IMG_1737.JPG
Type: image/jpeg
Size: 1655096 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/lerftest/attachments/20181004/de4904b4/attachment-0001.jpe>
More information about the Lerftest
mailing list