WAG LERF Schedule*
Kevin Jordan Aug. 12, 2020
*straw-person, subject to many changes
Aug 16 – 22
• Cancel 1X power supply move – change to end of September
• Finish LCLS-II CM 20 cryo testing
Aug 23 – 29
• Additional CM 20 LLRF testing?
• Check cathode Qe – receisiate as needed
• Check drive laser
Aug 30 – Sep 5
• HCO for Isotope run
• Check SRF cavity tune
Sep 6 – 12
• Labor Day
• Re-Commission beam to 1 g, then to 1X – What to use for beam dump at 1X?
Sep 13 – 19
• Irradiate Ga71 – 1 kilowatt for 1 hour & check gamma spec to validate models
Sep 20 – 26
• Remove shield blocks from LERF vault
• Move 1X power supply to GTS
Sep 27 – Oct 3
• CEBAF to 4.2K
• Pull U-Tubes from LCLS-II CM 20
• Remove CM 20 from LERF
Oct 4 – 10
• Move LCLS-II CM 11 & reinstall shield blocks
• Connect CM 11 cables & waveguide
Oct 11 – 17
• Cooldown CM 11 to 4.2 K
Oct 18 – 24
• CEBAF South Linac to 2 K
• Cooldown CM 11 to 2 K & refill
Oct 25 – 31
• CM 11 testing
Nov 1 – 7
• CM 11 testing
Nov 8 – 14
• CM 11 Testing
Nov 15 – 21
• Remove shield blocks & CM 11 & SSAs
Nov 22 – 28
• Thanksgiving
Over the next year there can be opportunistic running - in general CEBAF south linac will be at 4.2 K & can be pumped down to 2 K to facilitate isotope running periodically. Starting in the summer of 2021 the LCLS-II HE modules will be tested one every couple months for ~ 2 years until 2023.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/lerftest/attachments/20200812/d8c158b7/attachment-0001.html>
More information about the Lerftest
mailing list