  Minutes of the August 11 meeting


       From Lowqwiki

Present: Stepan, Aji, Andrea, Maurizio B., Hovanes

On the phone: Raffaella, Katya, Kawtar

Notes by Hovanes


    Contents

[hide <javascript:toggleToc()>]

    * 1 RTPC contruction
      <http://clasweb.jlab.org/rungroups/lowq/wiki/index.php/Minutes_of_the_August_11_meeting#RTPC_contruction>
    * 2 Electronics upgrade
      <http://clasweb.jlab.org/rungroups/lowq/wiki/index.php/Minutes_of_the_August_11_meeting#Electronics_upgrade>
    * 3 Gas system
      <http://clasweb.jlab.org/rungroups/lowq/wiki/index.php/Minutes_of_the_August_11_meeting#Gas_system>
    * 4 Other issues
      <http://clasweb.jlab.org/rungroups/lowq/wiki/index.php/Minutes_of_the_August_11_meeting#Other_issues>

[edit 
<http://clasweb.jlab.org/rungroups/lowq/wiki/index.php?title=Minutes_of_the_August_11_meeting&action=edit&section=1>]


    RTPC contruction

    Stepan gave an update on the construction of the main RTPC.

        * Two new foil assemblies are ready.
        * PCB board assembly is ready for being populated.
        * Stepan and Andrea will start gluing GEMs on the support after
          the meeting.
        * Andrea will be using a color map to label the wires instead of
          attaching paper labels to make it easier to work with them.
        * Beginning of the next week the main part of the assembly of
          the RTPC will be complete.
        * There is a slight designing issues with the O-ring on the
          downstream plate where a screw head might interfere preventing
          the O-ring from sealing tight. Stepan did not think it will be
          difficult to deal with.
        * The divider was ordered with correct mounting hole locations.
          The holes one on the one on the prototype did not have the
          holes in the right place (misplaced by 1/2mm), and it was
          taped instead.
        * Stephen tested the prototype with the Neon/DME gas and got
          good signals. He will run it with Helium/DME gas mixture to
          compare the signal with what Bonus got with the old RTPC.
        * We have the beamline drawings, Stepan will send them to
          Hovanes to be posted on wiki. Stepan already noticed some
          possible mistakes on the drawing, like the target exit window
          should be 15 ?m not 25 ?m . The drawing should be checked and
          the feedback send to Stepan or Pete Hemler.

[edit 
<http://clasweb.jlab.org/rungroups/lowq/wiki/index.php?title=Minutes_of_the_August_11_meeting&action=edit&section=2>]


    Electronics upgrade

    Raffaella reported on the progress with the readout electronics.

        * New crates and readout controllers are in the counting house.
        * The new firmware from CERN was tested successfully.
        * Sergey started the integration with the CLAS DAQ system and
          already is able to read events. More improvements are needed.
        * At this point there is no possibility to have a multipevent
          buffer and a sparcified readout list. Experts at CERN are
          trying to find a solution, and they promised to get back to
          Genova by the last weekend. But Raffaella still has not heard
          from them.
        * With current configuration we can read 0-size events are
          2.5kHz rate.
        * Raffaella and Stepan think that we should try to double the
          number of RCUs, extending the event rate to 3.6kHz max. For
          that we would need PCIS boards, RCUs, DCSs and new PCs.
        * Genova will send the new backplanes and cards to JLab. The new
          crates will be assembled at JLab.

[edit 
<http://clasweb.jlab.org/rungroups/lowq/wiki/index.php?title=Minutes_of_the_August_11_meeting&action=edit&section=3>]


    Gas system

    Hovanes gave a brief update on the gas system.

        * The design of the system is finalized. George is working on
          the layout of the components.
        * The plate for the gas panel will be cut sometimes this week.
        * Maurizio Bertoldi from FSU is here to help with the assembly
          and testing of the gas panel.

[edit 
<http://clasweb.jlab.org/rungroups/lowq/wiki/index.php?title=Minutes_of_the_August_11_meeting&action=edit&section=4>]


    Other issues

        * Katya needs the solenoid field map in a format compatable with
          Garfield, like TOSCA output format. Present collaborators were
          not sure if it exists. F.-X. is apparently looking into it.
        * We also briefly discussed the issue of possible lower beam
          polarization and it's impact.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/lowq/attachments/20090812/daefae5d/attachment.html 


More information about the Lowq mailing list