Location: CEBAF Center F113
Wednesday, August 12:
8:45 - 9:00 BlueJeans Setup
9:00 - 9:30 Input from JLab Management (R. McKeown/R. Ent/C. Keppel)
9:30 - 9:55 Status Report (K. Kumar)
9:55 - 10:15 Next Steps (M. Pitt)
10:15 - 10:30 Discussion
10:30 - 10:45 Coffee
10:45 - 11:15 Spectrometer Update (J. Mammei)
11:15 - 11:45 Toroid Engineering (E. Ihloff)
11:45 - 12:00 Discussion
12:00 - 1:30 Lunch
1:30 - 1:45 Status of 2-loop calculations (A. Aleksejevs)
1:45 - 2:15 Polarized Source and Polarized Beam (K. Paschke)
2:15 - 2:45 Beam Monitoring (M. Pitt)
2:45 - 3:00 Discussion
3:00 - 3:15 Target and Cooling (J. Gomez)
3:15 - 3:30 Discussion
3:30 - 3:45 Coffee
3:45 - 4:00 Simulations Overview (S. Riordan)
4:00 - 4:10 Collimation (K. Kumar)
4:10 - 4:20 Raster Study (R. Silwal)
4:20 - 4:45 Shielding (R. Beminiwattha)
4:45 - 5:00 Discussion
Thursday, August 13:
8:45-9:05 Overview/Project Management/Test beam results (M. Gericke)
9:10-9:30 Test beam results and Shower Max Detector (D. McNulty)
9:30-9:45 Test Beam Scintillation Data Analysis (K. Kumar)
9:45-10:00 Pion detector (W. Deconinck)
10:00-10:15 Discussion
10:15 - 10:30 Coffee
10:30 - 10:45 Electronics/DAQ (R. Michaels)
10:45 - 11:00 Discussion
11:00 - 11:15 Inelastic e-p background strategy (S. Riordan)
11:15 - 11:30 Aluminum Background Brainstorming (M. Pitt)
11:30 - 11:45 Pion Background Brainstorming (P. Souder)
11:45 - 12:00 Summary Discussion
12:00 - 1:30 Lunch
1:30 - 1:55 Compton Polarimetry (D. Gaskell)
1:55 - 2:15 Moller Polarimetry (J. Napolitano)
2:15 - 2:30 Discussion
2:30 - 2:45 Tracking analysis (S. Riordan)
2:45 - 3:00 GEMs (N. Liyanage)
3:00 - 3:15 Discussion
3:15 - 3:30 Coffee
3:30 - 4:00 Hall A Infrastructure (J. Gomez)
4:00 - 4:30 Project Management Plan (J. Gomez)
4:30 - 5:00 Summary Discussion and Planning
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/moller/attachments/20150805/37aaa242/attachment.html>
More information about the Moller
mailing list