[Moller] [Jlab-scicomp-briefs] JLab Data Center cooling work completed

Bryan Hess via Jlab-scicomp-briefs jlab-scicomp-briefs at jlab.org
Thu Aug 10 16:37:39 EDT 2023


Today's scheduled data center cooling work has been completed. All clusters are now running jobs. Interactive machines and Jupyter hub are online.

Tape Library operations, including jget, jput, and jcache will resume tomorrow morning at 8:00am.

As a reminder, next Thursday August 17th is a second data center outage, this time for electrical maintenance work.

Please report any unexpected issues using ServiceNow <https://jlab.servicenowservices.com/scicomp>


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/moller/attachments/20230810/7d61dac4/attachment.html>
-------------- next part --------------
--

This is an announcement-only list for Jefferson Lab Scientific Computing Updates .

Subscription and List Archive: https://mailman.jlab.org/mailman/listinfo/jlab-scicomp-briefs

For help: https://jlab.servicenowservices.com/scicomp


More information about the Moller mailing list