We have received the final report from the review.  It is linked at the top of the main page for the review.
Direct link is https://jeffersonlab.sharepoint.com/:b:/r/sites/MOLLER/Shared%20Documents/Reviews/IPR%20January%202023/2301%20MOLLER%20CD-3A%20Rpt.pdf?csf=1&web=1&e=QC9N2F

Key Recommendations:

  *   Proceed to CD-3A after updating cost estimates, risks, and the contingency analysis (for the    CD-3A scope).
  *   Work with TJNAF management to identify a full-time, experienced deputy Project Manager as soon as possible and address the other open positions.  Report on progress to the DOE Nuclear Physics Program Office by April 2023.
  *   Before the CD-2/3 review:
­   Develop further the Installation plan with finer granularity, to include staffing plan and preliminary installation drawings.
­   Complete the planned prototype detector tests.
­   Proceed with hire(s) into the DAQ group.
­   Prepare an assumptions document.

Jim

James Fast
MOLLER Project Manager
Jefferson Lab
757-230-6833 (cell)
757-269-5324 (office)

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/moller_l2/attachments/20230123/06e36e67/attachment.html>


More information about the Moller_L2 mailing list