[Moller_L2] IPR final report
James Fast
jfast at jlab.org
Mon Jan 23 16:30:00 EST 2023
Folks,
We have received the final report from the review. It is linked at the top of the main page for the review.
Direct link is https://jeffersonlab.sharepoint.com/:b:/r/sites/MOLLER/Shared%20Documents/Reviews/IPR%20January%202023/2301%20MOLLER%20CD-3A%20Rpt.pdf?csf=1&web=1&e=QC9N2F
Key Recommendations:
* Proceed to CD-3A after updating cost estimates, risks, and the contingency analysis (for the CD-3A scope).
* Work with TJNAF management to identify a full-time, experienced deputy Project Manager as soon as possible and address the other open positions. Report on progress to the DOE Nuclear Physics Program Office by April 2023.
* Before the CD-2/3 review:
Develop further the Installation plan with finer granularity, to include staffing plan and preliminary installation drawings.
Complete the planned prototype detector tests.
Proceed with hire(s) into the DAQ group.
Prepare an assumptions document.
Jim
James Fast
MOLLER Project Manager
Jefferson Lab
757-230-6833 (cell)
757-269-5324 (office)
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/moller_l2/attachments/20230123/06e36e67/attachment.html>
More information about the Moller_L2
mailing list