[Mott] Mott End Game
Joseph Grames
grames at jlab.org
Mon May 5 09:39:08 EDT 2014
In consultation with Arne and Noel-PD, the last 12 hours of the commissioning run (Friday, May 9th 00:00-12:00) are nominally ear-marked to complete four Mott related test plans requiring both the INJ and NL in Beam Permit.
The tasks are here:
Mott for commissioning - http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14221
Mott for MFL0I07 - http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14220
Here's the plan:
Wed, May 7th
DAY
(1h) (Hansknecht, Grames) No beam hook-up Hall C 31MHz laser, check phases
Fri, May 9th
0000
(4h) (Grames) Quantify target:dump events on all foils
(2h) (Suleiman) Test new semi-integrated-pedestal FADC mode
(1h) (McHugh) Charge asymmetry measurements
0700 ???
(1h) (DC Power, Grames) Injector access, DC power swap leads of one half of MFL0I07
(2h) (Grames) Mott measurement of phase advance
If no probs we wrap up by 10am.
More information about the Mott
mailing list