[Mott] Mott test update
Joseph Grames
grames at jlab.org
Thu May 8 15:41:03 EDT 2014
All - The program deputy informed me our Mott program start time is looking to be delayed between 0 to 8 hours. This means we could start on-time at midnight tonight, but more likely 4am, or even 8am Friday morning. So, if you are planning to come in for the Mott tests I would call the crew chief (x7097) this evening for an update, certainly before coming in. Or, have them page/call you. I'm the scheduled OWL LASO, so if optics folks agree I'll just plan to come in overnight when we "start" the Mott work. Also, Arne has extended operations through Friday SWING in order to complete the queued up work.
Simon - Our magnet re-wiring test will still happen, but is looking to be delayed to sometime on DAY shift. :)