[Pansophy] FW: New DocuShare document routing task (Step 1 Completion): SNS PPU Cryomodule Supply End Can CMA Receiving Inspection Traveler
Gary Cheng
cheng at jlab.org
Wed Nov 11 10:03:21 EST 2020
Hi Allen,
I see in DocuShare, the title for this one is SNSPPU-CMA-SENC-INSP. I
guess you want the corresponding RENC traveler to be titled as
SNSPPU-CMA-RENC-INSP, right?
Thanks,
Gary
On 11/10/2020 2:28 PM, Allen Samuels wrote:
>
> The SNSPPU-CMA-SECN-INSP-R1 traveler has been renamed to
> SNSPPU-SMA-SEC-INSP-R1 and uploaded to pansophy.
>
> Allen Samuels
>
> *From:*DocuShare Workflow <docushare at jlab.org>
> *Sent:* Tuesday, November 10, 2020 8:58 AM
> *To:* Allen Samuels <samuels at jlab.org>
> *Subject:* New DocuShare document routing task (Step 1 Completion):
> SNS PPU Cryomodule Supply End Can CMA Receiving Inspection Traveler
>
> You have a new DocuShare document routing task:
>
> Subject: SNS PPU Cryomodule Supply End Can CMA Receiving Inspection
> Traveler
> Date: 11/10/2020 08:58:05
>
> Step 1 Completion:
>
> Gary Cheng, 11/06/2020 08:20:30 Approved:
>
> Larry King, 11/09/2020 15:56:50 Approved:
>
> John Fischer, 11/09/2020 09:54:53 Approved:
>
> Ed Daly, Edward, 11/10/2020 08:58:03 Approved:
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20201111/3f66ace6/attachment-0001.html>
More information about the Pansophy
mailing list