The procedure is now in the Approved Procedures folder in DocuShare

From: Megan McDonald <megan at jlab.org>
Sent: Wednesday, October 21, 2020 8:47 AM
To: Allen Samuels <samuels at jlab.org>
Subject: FW: New DocuShare document routing task (Step 1 Completion): Procedure Approval - CP-C75-CPR-ASSY-STBK-R1



From: DocuShare Workflow <docushare at jlab.org<mailto:docushare at jlab.org>>
Sent: Tuesday, October 20, 2020 10:31 AM
To: Megan McDonald <megan at jlab.org<mailto:megan at jlab.org>>
Subject: New DocuShare document routing task (Step 1 Completion): Procedure Approval - CP-C75-CPR-ASSY-STBK-R1

You have a new DocuShare document routing task:

Subject: Procedure Approval - CP-C75-CPR-ASSY-STBK-R1
Date: 10/20/2020 10:31:08

Step 1 Completion:

Chris Dreyfuss, 10/19/2020 06:40:46 Approved:

Danny Forehand, 10/09/2020 14:58:11 Approved:

Kurt Macha, 10/20/2020 10:31:08 Approved:

Gianluigi Ciovati, 10/02/2020 09:28:23 Approved:

Tony Reilly, 10/05/2020 13:02:04 Approved:
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20201021/b06a6e04/attachment.html>


More information about the Pansophy mailing list