Hello Valerie
Here is the last P1 Schedule I had seen (from 17Aug2020) , It is been being updated by Tony, and he has not sent an update yet - never the less it does give a good idea of when things are supposed to happen for P1 , even if it is not the very latest version
Anne
Task Name
Duration
Start
Finish
P1 Refurbishment
251 days
Thu 5/7/20
Fri 5/7/21
Disassembly
50 days
Thu 5/7/20
Wed 7/15/20
Crymodule Disassembly Completed
0 days
Wed 7/15/20
Wed 7/15/20
Cavity Prep and Test
70 days
Thu 7/16/20
Thu 10/22/20
Cavity Prep and Test Completed
0 days
Thu 10/22/20
Thu 10/22/20
String Assembly
15 days
Fri 10/23/20
Thu 11/12/20
String Assembly Completed
0 days
Thu 11/12/20
Thu 11/12/20
Space Frame Assembly
45 days
Fri 11/13/20
Thu 1/28/21
Space Frame Assembly Completed
0 days
Thu 1/28/21
Thu 1/28/21
Cryomodule Assembly
45 days
Fri 1/29/21
Thu 4/1/21
Cryomodule Assembly Completed
0 days
Thu 4/1/21
Thu 4/1/21
Cryomodule Test
20 days
Mon 4/12/21
Fri 5/7/21
Cryomodule Test Completed
0 days
Fri 5/7/21
Fri 5/7/21
Install and Commission P1
15 days
Mon 5/10/21
Mon 5/31/21
_______________________________________________________________________________
E. Anne McEwen
JSA / Jefferson Lab
SRF Institute
Newport News, VA 23606
Office: +1 (757) 269-5539
Email: mcewen at jlab.org<mailto:mcewen at jlab.org>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20200928/e776bda3/attachment-0001.html>
More information about the Pansophy
mailing list