[Pansophy] FW: FW: SNS PPU new weld inspection travelers for approvals (Gary is saying these are needed NOW)

Valerie Bookwalter bookwalt at jlab.org
Tue Sep 29 11:23:50 EDT 2020


What do you have on these?


From: Gary Cheng <cheng at jlab.org>
Sent: Tuesday, September 29, 2020 11:22 AM
To: E. Anne McEwen <mcewen at jlab.org>
Cc: Valerie Bookwalter <bookwalt at jlab.org>; Katherine Wilson <kwilson at jlab.org>; Ed Daly <edaly at jlab.org>; Jenord Alston <jalston at jlab.org>
Subject: Re: FW: [Pansophy] SNS PPU new weld inspection travelers for approvals

Hi Anne,

These are urgent. That's why I created them immediately. They are used to inspect PPU corrguated hoses and He Outlet Bellows and Con Bellows made by Hyspan.

Lately, as you may have heard, a subcontractor reported weld quality issues with Hyspan's hoses that they bought. PPU team then decides to inspect the hoses and bellows made by Hyspan, delivered to JLab, right away to size the problem. Jenord has done his initial evaluation and found some hoses having weld issues. We need the travelers for Jenord to use to document whatever results he concludes. Should there be NCR(s), we will go through the process to take care of them.

Thanks,
Gary
On 9/29/2020 10:36 AM, E. Anne McEwen wrote:
Hi Gary

We are trying to figure our priorities for travelers and other work  (cannot do everything at once)  - when will the parts be used where these travelers are required ?

Can you tell me what parts this weld inspection  applies to ?

Thanks Anne

From: Valerie Bookwalter <bookwalt at jlab.org><mailto:bookwalt at jlab.org>
Sent: Tuesday, September 29, 2020 10:34 AM
To: E. Anne McEwen <mcewen at jlab.org><mailto:mcewen at jlab.org>
Subject: FW: [Pansophy] SNS PPU new weld inspection travelers for approvals



From: Pansophy <pansophy-bounces at jlab.org<mailto:pansophy-bounces at jlab.org>> On Behalf Of Valerie Bookwalter
Sent: Tuesday, September 29, 2020 10:13 AM
To: Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>
Cc: SRF Pansophy (pansophy at jlab.org<mailto:pansophy at jlab.org>) <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: Re: [Pansophy] SNS PPU new weld inspection travelers for approvals

So where do these fit into the CMM/Visual inspection que?

From: Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>
Sent: Tuesday, September 29, 2020 9:51 AM
To: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Cc: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: Re: [Pansophy] SNS PPU new weld inspection travelers for approvals

Hi Anne,

These travelers are used to inspect welds done by vendors on parts already delivered to us.

Thanks,
Gary

________________________________
From: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Sent: Monday, September 28, 2020 3:27 PM
To: Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>
Cc: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: FW: [Pansophy] SNS PPU new weld inspection travelers for approvals


Hi Gary - Could you tell me when the welding  you mention in these travelers will start ?



Which component is being welded ?



Is there a planned start and end date for this welding that you and the project have in mind



Thanks Anne



From: Pansophy <pansophy-bounces at jlab.org<mailto:pansophy-bounces at jlab.org>> On Behalf Of Gary Cheng
Sent: Monday, September 28, 2020 1:17 PM
To: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: [Pansophy] SNS PPU new weld inspection travelers for approvals



Hi Team,

I just uploaded a couple weld inspection travelers: SNSPPU-INSP-HOBCB-WELD & SNSPPU-INSP-EQFH-WELD, to DocuShare. Please initiate the approval process.

Thanks,
Gary

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20200929/9ef32d00/attachment-0001.html>


More information about the Pansophy mailing list