[Pansophy] FW: P1 Travelers for Chemistry etc. ?
Valerie Bookwalter
bookwalt at jlab.org
Tue Sep 29 16:50:24 EDT 2020
From: E. Anne McEwen <mcewen at jlab.org>
Sent: Tuesday, September 29, 2020 1:18 PM
To: Ashley Anderson Mitchell <ashleya at jlab.org>
Cc: Valerie Bookwalter <bookwalt at jlab.org>
Subject: RE: P1 Travelers for Chemistry etc. ?
Thanks Ashley !
Best wishes
Anne
From: Ashley Anderson Mitchell <ashleya at jlab.org<mailto:ashleya at jlab.org>>
Sent: Tuesday, September 29, 2020 1:14 PM
To: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Cc: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: Re: P1 Travelers for Chemistry etc. ?
Anne,
We're doing well with many P1 travelers sent to pansophy already. Alex has been working on them when he has to work from home. We should have travelers written for: lapping, HPR, HEP, cavity degrease, and acid etching.
We'll cc you on future submissions.
________________________________
From: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Sent: Tuesday, September 29, 2020 12:52 PM
To: Ashley Anderson Mitchell <ashleya at jlab.org<mailto:ashleya at jlab.org>>
Cc: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: FW: P1 Travelers for Chemistry etc. ?
Hi Ashley
We were wondering how you were doing with the travelers for P1 ?
Kurt Macha mentioned that the string starts in 8 weeks , so we are trying to prepare - we have had a number of travelers come in this week ready to send out for final approval , and so are attempting to get as many into the system as possible for the work up to the end of the string assembly
Attached is the last Master traveler list as found in Docushare - if you have travelers that are ready to get out for approval could you please send them to Valerie and Pansophy @JLAB.org. Please copy me so I know the draft has been released to the Pansophy Team
Please let me know if you need any help
Anne
From: E. Anne McEwen
Sent: Monday, September 28, 2020 3:06 PM
To: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: P1 Scheduled for Mid August
Hello Valerie
Here is the last P1 Schedule I had seen (from 17Aug2020) , It is been being updated by Tony, and he has not sent an update yet - never the less it does give a good idea of when things are supposed to happen for P1 , even if it is not the very latest version
Anne
Task Name
Duration
Start
Finish
P1 Refurbishment
251 days
Thu 5/7/20
Fri 5/7/21
Disassembly
50 days
Thu 5/7/20
Wed 7/15/20
Crymodule Disassembly Completed
0 days
Wed 7/15/20
Wed 7/15/20
Cavity Prep and Test
70 days
Thu 7/16/20
Thu 10/22/20
Cavity Prep and Test Completed
0 days
Thu 10/22/20
Thu 10/22/20
String Assembly
15 days
Fri 10/23/20
Thu 11/12/20
String Assembly Completed
0 days
Thu 11/12/20
Thu 11/12/20
Space Frame Assembly
45 days
Fri 11/13/20
Thu 1/28/21
Space Frame Assembly Completed
0 days
Thu 1/28/21
Thu 1/28/21
Cryomodule Assembly
45 days
Fri 1/29/21
Thu 4/1/21
Cryomodule Assembly Completed
0 days
Thu 4/1/21
Thu 4/1/21
Cryomodule Test
20 days
Mon 4/12/21
Fri 5/7/21
Cryomodule Test Completed
0 days
Fri 5/7/21
Fri 5/7/21
Install and Commission P1
15 days
Mon 5/10/21
Mon 5/31/21
_______________________________________________________________________________
E. Anne McEwen
JSA / Jefferson Lab
SRF Institute
Newport News, VA 23606
Office: +1 (757) 269-5539
Email: mcewen at jlab.org<mailto:mcewen at jlab.org>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20200929/b6aac953/attachment-0001.html>
More information about the Pansophy
mailing list