[Pansophy] FW: P1 Travelers for Chemistry etc. ?

Valerie Bookwalter bookwalt at jlab.org
Tue Sep 29 16:50:24 EDT 2020



From: E. Anne McEwen <mcewen at jlab.org>
Sent: Tuesday, September 29, 2020 1:18 PM
To: Ashley Anderson Mitchell <ashleya at jlab.org>
Cc: Valerie Bookwalter <bookwalt at jlab.org>
Subject: RE: P1 Travelers for Chemistry etc. ?

Thanks Ashley !

Best wishes

Anne

From: Ashley Anderson Mitchell <ashleya at jlab.org<mailto:ashleya at jlab.org>>
Sent: Tuesday, September 29, 2020 1:14 PM
To: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Cc: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: Re: P1 Travelers for Chemistry etc. ?

Anne,
We're doing well with many P1 travelers sent to pansophy already.  Alex has been working on them when he has to work from home. We should have travelers written for: lapping, HPR, HEP, cavity degrease, and acid etching.

We'll cc you on future submissions.
________________________________
From: E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Sent: Tuesday, September 29, 2020 12:52 PM
To: Ashley Anderson Mitchell <ashleya at jlab.org<mailto:ashleya at jlab.org>>
Cc: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: FW: P1 Travelers for Chemistry etc. ?


Hi Ashley



We were wondering how you were doing with the travelers for P1 ?



Kurt Macha mentioned that the string starts in 8 weeks , so we are trying to prepare - we have had a number of travelers come in this week ready to send out for final approval , and so are attempting to get as many into the system as possible for the work up to the end of the string assembly



Attached is the last Master traveler list as found in Docushare - if you have travelers that are ready to get out for approval could you please send them to Valerie and Pansophy @JLAB.org.  Please copy me so I know the draft has been released to the Pansophy Team



Please let me know if you need any help



Anne



From: E. Anne McEwen
Sent: Monday, September 28, 2020 3:06 PM
To: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Subject: P1 Scheduled for Mid August



Hello Valerie



Here is the last P1 Schedule I had seen (from 17Aug2020)  , It is been being updated by Tony, and he has not sent an update yet  - never the less it does give a good idea of when things are supposed to happen for P1 , even if it is not the very latest version



Anne





Task Name

Duration

Start

Finish

P1 Refurbishment

251 days

Thu 5/7/20

Fri 5/7/21

   Disassembly

50 days

Thu 5/7/20

Wed 7/15/20

   Crymodule Disassembly Completed

0 days

Wed 7/15/20

Wed 7/15/20

   Cavity Prep and Test

70 days

Thu 7/16/20

Thu 10/22/20

   Cavity Prep and Test Completed

0 days

Thu 10/22/20

Thu 10/22/20

   String Assembly

15 days

Fri 10/23/20

Thu 11/12/20

   String Assembly Completed

0 days

Thu 11/12/20

Thu 11/12/20

   Space Frame Assembly

45 days

Fri 11/13/20

Thu 1/28/21

   Space Frame Assembly Completed

0 days

Thu 1/28/21

Thu 1/28/21

   Cryomodule Assembly

45 days

Fri 1/29/21

Thu 4/1/21

   Cryomodule Assembly Completed

0 days

Thu 4/1/21

Thu 4/1/21

   Cryomodule Test

20 days

Mon 4/12/21

Fri 5/7/21

   Cryomodule Test Completed

0 days

Fri 5/7/21

Fri 5/7/21

Install and Commission P1

15 days

Mon 5/10/21

Mon 5/31/21







_______________________________________________________________________________

E. Anne McEwen

JSA / Jefferson Lab

SRF Institute

Newport News, VA 23606

Office: +1 (757) 269-5539

Email:   mcewen at jlab.org<mailto:mcewen at jlab.org>


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20200929/b6aac953/attachment-0001.html>


More information about the Pansophy mailing list