[Pansophy] FW: Doglegs
E. Anne McEwen
mcewen at jlab.org
Tue Feb 23 10:12:23 EST 2021
FYI- some of the complications when parts are being used across projects that we talked about yesterday - here is another example
The Dog legs are coming off a C50 , originally were to have gone on a C75 , but instead will do to the NBSN Pair because there is a shortage of acceptable dog legs
Just an example - Anne
From: George DeKerlegand <georged at jlab.org>
Sent: Tuesday, February 23, 2021 9:54 AM
To: E. Anne McEwen <mcewen at jlab.org>; Kurt Macha <macha at jlab.org>; Danny Forehand <forehand at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: Doglegs
Hi all,
Should dogleg DL-2 and DL-17 data go into NB3Sn or C75 project?
Thanks,
Aaron