Hi Frank,
sorry, I did not notice the comment. I think it's ok to leave a step for a visual inspection of the flanges in the tuning work center , in order to catch where a possible damage might have occurred during the processing.
Thanks,
Gigi
________________________________
From: Marhauser <marhause at jlab.org>
Sent: Friday, January 8, 2021 10:40 AM
To: Allen Samuels <samuels at jlab.org>; Gianluigi Ciovati <gciovati at jlab.org>; Danny Forehand <forehand at jlab.org>; Kurt Macha <macha at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: Re: FW: New DocuShare document routing task (Step 1 Completion): C75 Warm Cavity RF Tuning Measurements
Hi Allen,
Sorry, I have not seen a change yet in the document that concerns my comment for step 5.
That was my main point. It makes not much sense to me to get the same document re-routed now the 2nd
time without considering the comment. I understand that there were other issues with filename formatting, but
I do/did not not really care about this.
Frank
On 1/7/2021 4:24 PM, Allen Samuels wrote:
Hi Frank. Sorry it took me so long to get to your traveler.
I gave it a quick once-over to make sure it was good before routing. It’s mostly good, but there are issues with the file upload in step 10. The fieldname is too long, and periods in the fieldname do not work. Please make the necessary changes and upload the new version to the same folder.
Allen
From: Marhauser <marhause at jlab.org><mailto:marhause at jlab.org>
Sent: Thursday, January 7, 2021 9:49 AM
To: Allen Samuels <samuels at jlab.org><mailto:samuels at jlab.org>; Gianluigi Ciovati <gciovati at jlab.org><mailto:gciovati at jlab.org>; Danny Forehand <forehand at jlab.org><mailto:forehand at jlab.org>; Kurt Macha <macha at jlab.org><mailto:macha at jlab.org>
Cc: pansophy <pansophy at jlab.org><mailto:pansophy at jlab.org>
Subject: Re: FW: New DocuShare document routing task (Step 1 Completion): C75 Warm Cavity RF Tuning Measurements
Hi Allen,
Please send a link to that folder.
Frank
On 1/7/2021 8:58 AM, Allen Samuels wrote:
Hi Frank. To get the correct version routed, drop it in the C75 ready for approvals folder. I’ll upload it as a new version and create a routing slip.
Allen
From: DocuShare Workflow <docushare at jlab.org><mailto:docushare at jlab.org>
Sent: Thursday, January 7, 2021 8:52 AM
To: Allen Samuels <samuels at jlab.org><mailto:samuels at jlab.org>
Subject: New DocuShare document routing task (Step 1 Completion): C75 Warm Cavity RF Tuning Measurements
You have a new DocuShare document routing task:
Subject: C75 Warm Cavity RF Tuning Measurements
Date: 01/07/2021 08:51:45
Step 1 Completion:
Gianluigi Ciovati, 12/23/2020 10:32:43 Approved:
Danny Forehand, 01/07/2021 08:24:45 Approved:
Frank Marhauser, 01/07/2021 08:51:45 Disapproved: Comments included in traveler after review. How can I upload the reviewed file here?
Kurt Macha, 01/07/2021 08:13:23 Approved:
To view your pending document routing tasks, click on the link below to login to DocuShare:
https://jlabdoc.jlab.org/docushare/dsweb/routing/routing_email.jsp?url=report_base.jsp&reportType=ForApprovalCompletion&routingSlipRequestID=14744¬ifyID=14755&workFlowJobName=14744
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210108/3acfd117/attachment-0001.html>
More information about the Pansophy
mailing list