[Pansophy] C50R Traveler ?? C50R-CU-BRAZ-WINW ??
Valerie Bookwalter
bookwalt at jlab.org
Thu Jan 14 09:49:43 EST 2021
Good Morning Leonard,
The 1200 series windows as shown in the picture below are the one you are talking about, right?
Does this data need to be uploaded with these travelers that were already completed?
Most are from 2016-2018. If the data is from this time frame we could, with permission, re-open these travelers so you can add data.
If this is new data, more recent, you could open new travelers and add the data.
Since these windows are being used for C50's currently in the tunnel, to me, it seems the data should stay with the C50R project.
If these windows will be used for C75, then we should put the data there.
When the C50 that will be rebuilt this year is started (C50-01R cryomodule), the data will be put into the C50R project area.
Please let me know if I should re-open these travelers, and which one, or if I need to have this traveler moved to another area.
Thanks for your patience as I try to figure this out.
[cid:image002.jpg at 01D6EA5A.94B6C310]
Valerie Bookwalter
Jefferson Lab, SRF Department
Pansophy Team
1-757-813-6716 (CELL)
1-767-269-5802 (OFFICE - currently working offsite)
From: Leonard Page <lpage at jlab.org>
Sent: Thursday, January 14, 2021 7:39 AM
To: Valerie Bookwalter <bookwalt at jlab.org>
Cc: Michael Drury <drury at jlab.org>; Frank Humphry <fhumphry at jlab.org>; John Fischer <fischer at jlab.org>
Subject: Re: C50R Traveler ?? C50R-CU-BRAZ-WINW ??
Good Morning Val, The windows I'm testing are spare and replacement windows currently being used by Frank during the down as he 's removing all remaining poly windows and older versions of ceramics.
The series of windows now being tested (1200s) are listed in the C50R traveler.
Maybe they should be in the C75 folder
Several older cryomodules (C20s)already have new version of these windows installed previously and may not have to be replaced and may just need chemistry/cleaning and reuse.
In other words when refurbishing C50s they have this version of windows, when it's C20's to C75 most will have this version of windows and those that don't will use these, and unless told otherwise we won't be retesting older tested windows.
But we can't just sit on the test data until a folder is open.
LP
________________________________
From: Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Sent: Wednesday, January 13, 2021 4:44 PM
To: Leonard Page <lpage at jlab.org<mailto:lpage at jlab.org>>; pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Cc: Michael Drury <drury at jlab.org<mailto:drury at jlab.org>>; John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>; Ed Daly <edaly at jlab.org<mailto:edaly at jlab.org>>; E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>
Subject: RE: C50R Traveler ?? C50R-CU-BRAZ-WINW ??
Leonard,
I am just catching up on this conversation...
The C50R area is not yet ready for "new" data.
The data you are trying to enter is for C50R being built later this year?
Or another project? P1? C100R?
Please let me know how I can help you? Or if this problem has been resolved.
Valerie Bookwalter
Jefferson Lab, SRF Department
Pansophy Team
1-757-813-6716 (CELL)
1-767-269-5802 (OFFICE - currently working offsite)
From: Leonard Page <lpage at jlab.org<mailto:lpage at jlab.org>>
Sent: Monday, January 11, 2021 1:53 PM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>; E. Anne McEwen <mcewen at jlab.org<mailto:mcewen at jlab.org>>; Valerie Bookwalter <bookwalt at jlab.org<mailto:bookwalt at jlab.org>>
Cc: Michael Drury <drury at jlab.org<mailto:drury at jlab.org>>; John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>; Ed Daly <edaly at jlab.org<mailto:edaly at jlab.org>>
Subject: C50R Traveler
Allen I'm still testing C50R windows and the C50R traveler seems to be closed for input including the 1200 series windows dating back to 2018. I tried to input data ,grayed out blocks tell me it's close right?
I'd like to get caught up in the traveler on the 10 I've tested last October and the 20-plus currently being tested .
C50R-CU-BRAZ-WINW
I'm trying to time it so the recent batch P100 and the C100R windows just tested and being sent to the vendor for another round of coatings won't keep me behind on data input.
Thanks
LP
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210114/c0b2350a/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.jpg
Type: image/jpeg
Size: 67276 bytes
Desc: image002.jpg
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210114/c0b2350a/attachment-0001.jpg>
More information about the Pansophy
mailing list