[Pansophy] VV inspection naming
Valerie Bookwalter
bookwalt at jlab.org
Fri Jan 22 10:50:43 EST 2021
Morning Matt,
The VV is slightly different because it doesn't actually go into the "CMM Room" for inspection and part of the inspection is done by a WCA other than INSP (Anne's group). So, we put it under CMA (cryomodule assembly area) to better handle cross Work centers. The INSP should be an ACTION as well as a WCA. I will check my acronym listing.
SNSPPU-CMA-VV-INSP is the correct naming for this component. I will update the acronym listing.
Thank you for your help.
Valerie
________________________________
From: Pansophy <pansophy-bounces at mailman.jlab.org> on behalf of Matt Marchlik <marchlik at jlab.org>
Sent: Thursday, January 21, 2021 1:44 PM
To: pansophy <pansophy at jlab.org>
Subject: [Pansophy] VV inspection naming
Hi All,
My vac vessel inspection traveler was named SNSPPU-INSP-VV back when I created it. but now I see it is incorrect. I'm going through the acronyms and think it should be named SNSPPU-CMA-VV-INSP but I see that the action INSP is no longer available. What is the appropriate action for a traveler containing visual inspection and dimensional measurement steps?
Matt
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210122/004f5042/attachment.html>
More information about the Pansophy
mailing list