The C75-CPR-INSP-DGLG-R5 traveler is approved and uploaded to pansophy.

Allen

From: DocuShare Workflow <docushare at jlab.org>
Sent: Monday, January 25, 2021 7:00 AM
To: Allen Samuels <samuels at jlab.org>
Subject: New DocuShare document routing task (Step 1 Completion): Cebaf Cryomodule Dogleg Window Assembly

You have a new DocuShare document routing task:

Subject: Cebaf Cryomodule Dogleg Window Assembly
Date: 01/25/2021 06:59:48

Step 1 Completion:

George DeKerlegand, 01/25/2021 06:59:48 Approved:

Scott Williams, 01/22/2021 07:29:18 Approved:

Kurt Macha, 01/22/2021 09:20:58 Approved: