[Pansophy] C50R Traveler Dates

Allen Samuels samuels at jlab.org
Tue Jun 15 16:41:44 EDT 2021


Thanks, Ashley. There's another document I had a question on, CP-STP-CAV-CHEM-DEGR. It's an STP traveler in the C75 masterlist. It is listed as not complete, but there's an R3 in the STP approved procedures folder. Is this procedure planned to be edited to fit C75, or is it good as is and is in the masterlist just so people know to use it?

Allen

From: Ashley Anderson Mitchell <ashleya at jlab.org>
Sent: Tuesday, June 15, 2021 3:58 PM
To: Allen Samuels <samuels at jlab.org>
Cc: pansophy at jlab.org
Subject: Re: C50R Traveler Dates

Allen,
Those travelers will be under energy reach once its all combined in a few weeks, so I wouldn't even bother, if you really need a date, make it 8/1/21 and hopefully it'll be gone by then . We'll be using the C75 versions of travelers once it's all combined.

-Ashley
________________________________
From: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Sent: Tuesday, June 15, 2021 2:16:32 PM
To: Ashley Anderson Mitchell <ashleya at jlab.org<mailto:ashleya at jlab.org>>
Cc: pansophy at jlab.org<mailto:pansophy at jlab.org> <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: C50R Traveler Dates


Ashley,



I'm contacting you regarding the C50R travelers that don't have a due date. These are C50R-CPR-BCP-SUBC, C50R-CPR-CLN-SUBC, and C50R-CPR-CHEM-CPR. Thanks.



Allen
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20210615/fd7f42f8/attachment.html>


More information about the Pansophy mailing list