[Pansophy] FW: New DocuShare document routing task (Step 1 Completion): Traveler Approval - SNSPPU-CLNRM-CST-LEAK-R1

Megan McDonald megan at jlab.org
Fri Mar 19 16:32:52 EDT 2021


This traveler is now in Pansophy

Megan

From: DocuShare Workflow <docushare at jlab.org>
Sent: Friday, March 19, 2021 3:52 PM
To: Megan McDonald <megan at jlab.org>
Subject: New DocuShare document routing task (Step 1 Completion): Traveler Approval - SNSPPU-CLNRM-CST-LEAK-R1

You have a new DocuShare document routing task:

Subject: Traveler Approval - SNSPPU-CLNRM-CST-LEAK-R1
Date: 03/19/2021 15:51:30

Step 1 Completion:

Danny Forehand, 03/19/2021 15:51:29 Approved:

Naeem Huque, 03/19/2021 13:48:29 Approved: Add huque to D3 emails

Ed Daly, Edward, 03/19/2021 15:02:48 Approved:

Kurt Macha, 03/19/2021 13:49:17 Approved:

I approved this traveler but have a couple comments.



  1.  The needle valve at the non pumping end of the string is closed and has atm. pressure with a blank on the far side.  May want to consider taping closed and tagging do not open.


  1.  Do we want to continue this traveler for next steps or write another for starting ion pump, preparing for transfer and transfer to next work center?









-------------- next part --------------