[Pansophy] FW: New DocuShare document routing task (Step 1 Completion): SRF-MSPR-CLNRM-CST-ION-R1.docx
Allen Samuels
samuels at jlab.org
Mon Nov 22 10:28:48 EST 2021
The SRF-MSPR-CLNRM-CST-ION procedure has been approved and uploaded to pansophy.
Allen
From: DocuShare Workflow <docushare at jlab.org>
Sent: Monday, November 22, 2021 10:06 AM
To: Allen Samuels <samuels at jlab.org>
Subject: New DocuShare document routing task (Step 1 Completion): SRF-MSPR-CLNRM-CST-ION-R1.docx
You have a new DocuShare document routing task:
Subject: SRF-MSPR-CLNRM-CST-ION-R1.docx
Date: 11/22/2021 10:05:51
Step 1 Completion:
Kirk Davis, 11/22/2021 10:05:49 Approved:
Danny Forehand, 11/12/2021 14:37:45 Approved:
Tony Reilly, 11/17/2021 12:16:02 Approved:
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20211122/d265cb77/attachment.html>
More information about the Pansophy
mailing list