[Pansophy] C75 Procedure to SRF Master Procedure?

John Fischer fischer at jlab.org
Wed Jul 13 14:12:15 EDT 2022


You are talking about the final assy traveler for snsppu? The revision notes were added for rev three



From: Allen Samuels <samuels at jlab.org>
Sent: Wednesday, July 13, 2022 2:09 PM
To: John Fischer <fischer at jlab.org>; Gary Cheng <cheng at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: RE: C75 Procedure to SRF Master Procedure?

John and Gary,

Good to hear. Something I just noticed however, the R2 is already in pansophy from September of last year. This means that this traveler is in fact an R3. I can turn this into an R3, but I need a revision note to add to the traveler. What should the note say?

Allen

From: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>
Sent: Wednesday, July 13, 2022 1:07 PM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>; Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>; Jacob Harris <jharris at jlab.org<mailto:jharris at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: RE: C75 Procedure to SRF Master Procedure?

In the meantime (prior to next traveler revision), we can review, edit, and put into the new template.
JF

From: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Sent: Wednesday, July 13, 2022 1:04 PM
To: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>; Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: RE: C75 Procedure to SRF Master Procedure?

Very well. I will upload the traveler as is.

Allen

From: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>
Sent: Wednesday, July 13, 2022 11:50 AM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>; Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: RE: C75 Procedure to SRF Master Procedure?

Allen,
This Traveler needs to go live asap. The Procedure for MLI can eventually be put into the Master Template but not now. Please proceed with the Traveler.
JF

From: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Sent: Wednesday, July 13, 2022 11:47 AM
To: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>; Gary Cheng <cheng at jlab.org<mailto:cheng at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: RE: C75 Procedure to SRF Master Procedure?

Gary,

Since you are the author of the traveler this is in, I thought I might also ask you about it as well.

Allen

From: Allen Samuels
Sent: Wednesday, July 13, 2022 11:43 AM
To: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: C75 Procedure to SRF Master Procedure?

John,

I was reviewing SNSPPU-CMA-CMASS-ASSY for upload when I noticed one of the procedure links went to a C75 procedure. I was wondering if this is something that we could turn into an SRF MSPR, since it's being used across multiple projects. This<https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-212972/CP-C75-CM-INST-MLI-R1.pdf> is the procedure in question, CP-C75-CM-INST-MLI.

Allen
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20220713/e66488d8/attachment.html>


More information about the Pansophy mailing list