The L2HE-CLNRM-CST-ASSY-R1 traveler has been uploaded to the Ready for Approval folder.


*         This version incorporates the lessons learned from the purge system commissioning run.

*         This version does not incorporate any lessons learned from the bellows assembly mockup scheduled for later this week.  I have sent this version of the traveler for review without waiting for this feedback in order to have an issued traveler in time for string assembly start.  If we determine that changes to the traveler step wording needs to be made for the first string assembly, I will capture those changes in a separate document that will be provided for use during string assembly.

*         This version does keep the formatting changes made by the Pansophy team.

*         The traveler references L2HE-PR-CLNRM-GV1SA-ASSY.  Revision 2 is currently in the approval process.  A hyperlink to the approved R2 version of this procedure can be added once L2HE-PR-CLNRM-GV1SA-ASSY-R2 is approved.

Cavity string assembly (using this traveler) is scheduled to start the week of 3/21.

https://jlabdoc.jlab.org/docushare/dsweb/View/Collection-49548


Tiffany Ganey

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20220308/a7694d4e/attachment.html>


More information about the Pansophy mailing list