Forwarding this so you get an update.
Allen
From: Michelle Oast <weinmann at jlab.org>
Sent: Thursday, May 4, 2023 8:50 AM
To: Adam Grabowski <adamg at jlab.org>
Cc: Allen Samuels <samuels at jlab.org>; Gary Cheng <cheng at jlab.org>; Liang Zhao <lzhao at jlab.org>
Subject: RE: L2HE-INSP Beamline Travelers
Hi Adam,
Thanks for the WCD, I added Gary instead of Anne for reviewer 2 and for NCR/D3 notification (see attached). Since I'm going to edit the bellows inspection travelers again it's no problem to change Gary to Anne and to remove Mike from D3 notifications, but I do think Gary should be included for NCRs and D3s since he's been helping me with travelers and with the upstream dents issues. Especially since I'll be going on maternity leave in late July/early August it would be good to have an extra person included who can disposition NCRs. Also, I think Liang should be included on the short bellows and extension spool (BLBS and BLXD) NCR dispositioners since they're also plated.
Let me know your thoughts, thanks.
Michelle
From: Adam Grabowski <adamg at jlab.org<mailto:adamg at jlab.org>>
Sent: Tuesday, May 2, 2023 2:58 PM
To: Michelle Oast <weinmann at jlab.org<mailto:weinmann at jlab.org>>
Subject: Re: L2HE-INSP Beamline Travelers
Michelle,
This is the document (attached) that the project coordinator (me) put together. There are a lot of restrictions on who can be what on this, but if I missed an NCR/D3 notification or dispositioner please let me know.
Adam Grabowski
SRF Test Engineer, L2HE Project CAM
Jefferson Lab
600 KELVIN DR Suite # 8
Mail Stop 55H
Newport News, VA 23606
O: 757-269-7665
C: 360-320-7003
E: adamg at jlab.org<mailto:adamg at jlab.org>
________________________________
From: Michelle Oast <weinmann at jlab.org<mailto:weinmann at jlab.org>>
Sent: Tuesday, May 2, 2023 2:10 PM
To: Adam Grabowski <adamg at jlab.org<mailto:adamg at jlab.org>>
Subject: FW: L2HE-INSP Beamline Travelers
Hi Adam,
Should Allen change the HE WCD? I'm not sure what that is or when it was last updated.
Thanks,
Michelle
From: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Sent: Monday, May 1, 2023 4:46 PM
To: Michelle Oast <weinmann at jlab.org<mailto:weinmann at jlab.org>>
Cc: pansophy at jlab.org<mailto:pansophy at jlab.org>; Adam Grabowski <adamg at jlab.org<mailto:adamg at jlab.org>>
Subject: L2HE-INSP Beamline Travelers
Michelle,
I was reviewing the R3 revisions of the beamline inspection travelers you put out today. I noticed that not all of the approval names and NCR/D3 emails match the L2HE WCD. Please confirm with Adam whether the travelers should change to reflect the WCD, or the WCD needs to be changed to reflect the traveler.
Allen
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20230504/84b1cb51/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: L2HE-INSP-BLBS-R3.docx
Type: application/vnd.openxmlformats-officedocument.wordprocessingml.document
Size: 215031 bytes
Desc: L2HE-INSP-BLBS-R3.docx
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20230504/84b1cb51/attachment-0001.docx>