[Pansophy] FW: L2HE Procedure Conversion

Allen Samuels samuels at jlab.org
Mon Apr 15 10:19:32 EDT 2024


Valerie,

This was the last update I got regarding the HE procedures we discussed. Does this change your instructions? I don't have an ID or approvals, or the earlier sections although those feel less important.

Allen

From: John Fischer <fischer at jlab.org>
Sent: Thursday, February 22, 2024 7:19 AM
To: Allen Samuels <samuels at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: RE: L2HE Procedure Conversion

Allen,
Thanks for the help. I will look at them.
JF

From: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Sent: Wednesday, February 21, 2024 5:13 PM
To: John Fischer <fischer at jlab.org<mailto:fischer at jlab.org>>
Cc: pansophy <pansophy at jlab.org<mailto:pansophy at jlab.org>>
Subject: L2HE Procedure Conversion

John,

I have moved over the Upstream Feed Cap and Downstream End Cap Installation procedures to the current procedure template. I was unable to fully fill them out, such as procedure ID, approvals, and the earlier sections, as I was unsure what to put in those. The documents have been uploaded to the draft L2HE procedures folder under their original name, plus my initials at the end. Please look over them and make any changes you deem necessary before putting them in ready for approvals. I will do the same for the L2HE cryomodule shipping procedure tomorrow.

Allen
-------------- next part --------------