[Pansophy] Updated ER5C Traveler for the pair - approvals ?

E. Anne McEwen mcewen at jlab.org
Thu Jan 25 14:54:17 EST 2024


Hi Aaron & Allen

The ER5 C Register has been approved , with the updated names (reference email from Allen below)

Valerie told me that Allen would be updating the traveler for the pair with the new names and sending it out, although he might have quite a number of travelers to update

So I was wondering if Aaron should update the names and resubmit it to Allen to be put into circulation for approval ?

We might be getting a pair mid of next week, so just wanted to be ready in case this happened

Anne



Document Title
Document Type
Document ID

Author / Owner
Reviewer 1 (SRFOPS SME or WCL)
Reviewer 2 (SRFOPS WCL or Group Lead)
Project Representative
NCR Informative
NCR Dispositioners
D3 Emails
CAVITY PAIR
C50R Cavity Pair Final Assembly  Dimensional Inspection
Traveler
ER5C-INSP-CPR-C50R-R1

A. DeKerlegand
J. Fischer
A. McEwen
A. Reilly
kdavis,areilly,mosby, georged
forehand,gciovati,fischer,kdavis,weaksmc
forehand,gciovati,fischer,kdavis,georged,mosby
C75 Cavity Pair Final Assembly Dimensional Inspection
Traveler
ER5C-INSP-CPR-R3

A. DeKerlegand
J. Fischer
A. McEwen
A. Reilly
kdavis,areilly,mosby,georged
forehand,gciovati,fischer,kdavis,weaksmc
forehand,gciovati,fischer,kdavis,georged,mosby



From: Allen Samuels <samuels at jlab.org>
Sent: Wednesday, January 24, 2024 3:29 PM
To: Matt Weaks <weaksmc at jlab.org>; Tiffany Ganey <ganey at jlab.org>; Philip Denny <denny at jlab.org>; E. Anne McEwen <mcewen at jlab.org>; Kirk Davis <kdavis at jlab.org>; John Fischer <fischer at jlab.org>; Michael Drury <drury at jlab.org>; Tony Reilly <areilly at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: FW: New DocuShare document routing task (Step 1 Completion): ER5C Work Control Document Register_19JAN24.xlsx

The ER5C Work Control Document Register has been approved and uploaded to docushare.

Allen

From: DocuShare Workflow <docushare at jlab.org<mailto:docushare at jlab.org>>
Sent: Tuesday, January 23, 2024 2:31 PM
To: Allen Samuels <samuels at jlab.org<mailto:samuels at jlab.org>>
Subject: New DocuShare document routing task (Step 1 Completion): ER5C Work Control Document Register_19JAN24.xlsx

You have a new DocuShare document routing task:

Subject: ER5C Work Control Document Register_19JAN24.xlsx
Date: 01/23/2024 14:30:44

Step 1 Completion:

Matt Weaks, 01/19/2024 15:26:03 Approved:

Tiffany Ganey, 01/22/2024 15:43:29 Approved:

Philip Denny, Philip, 01/19/2024 15:22:47 Approved:

E. Anne McEwen, E., 01/19/2024 15:22:52 Approved:

Kirk Davis, 01/22/2024 15:40:04 Approved:

John Fischer, 01/22/2024 10:25:27 Approved:

Michael Drury, 01/23/2024 07:33:01 Approved:

Tony Reilly, 01/23/2024 14:30:43 Approved:

To view your pending document routing tasks, click on the link below to login to DocuShare:

https://jlabdoc.jlab.org/docushare/dsweb/routing/routing_email.jsp?url=report_base.jsp&reportType=ForApprovalCompletion&routingSlipRequestID=37754&notifyID=37769&workFlowJobName=37754
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20240125/c4836c78/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: ER5C Work Control Document Register_19JAN24 (4).xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 98936 bytes
Desc: ER5C Work Control Document Register_19JAN24 (4).xlsx
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20240125/c4836c78/attachment-0001.xlsx>


More information about the Pansophy mailing list