Tiffany / Liang,
No INV traveler will be needed for the FT08P components. The information requested originally in the traveler is already being captured in the PRIMeS system.
We will process the INSP and CSHK travelers.
Tiffany, if you could update the C100R WCD Register and let us know when it is ready to be sent for approvals.
Thanks.
Valerie Bookwalter
Jefferson Lab, ACC
SRF Operations
SRFOPS Software Systems Group
1-757-269-5802 (OFFICE - currently working offsite)
From: Pansophy <pansophy-bounces at mailman.jlab.org> On Behalf Of Liang Zhao via Pansophy
Sent: Wednesday, February 28, 2024 4:12 PM
To: Allen Samuels <samuels at jlab.org>
Cc: Tiffany Ganey <ganey at jlab.org>; pansophy <pansophy at jlab.org>
Subject: [Pansophy] New travelers in "Ready for Approvals"
Hi Allen,
I have two travelers ready for approval. They are in the "Ready for Approvals" folder now.
C100R-CMA-FT08P-INSP-R1
C100R-VTA-FT08P-CSHK-R1
Thanks,
Liang
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20240306/68062a2c/attachment.html>
More information about the Pansophy
mailing list