Hi Megan,

That is correct for the upcoming month or so.  There is one traveler in for approval now, and we'll issue a couple new procedures for the start of PP in CEBAF this SAD.  After the SAD, several (unknown quantity) procedures may be updated based on lessons learned during the PP.  This will probably be around July or early August.

I'll update the WCD Register after I get the C75 PP procedures written and I'll try to remember to add the NA-CAL procedure.  Thanks!

Tiffany Ganey

From: Megan McDonald <megan at jlab.org>
Sent: Friday, May 17, 2024 8:54 AM
To: Tiffany Ganey <ganey at jlab.org>; Tom Powers <powers at jlab.org>
Cc: pansophy at jlab.org
Subject: PLACLN Meeting

Tiffany and Tom,

 Regarding the PLACLN stuff, the notes I have from the meeting are there will be 1-2 new procedures to account for the C75 CM plasma pricessing and the will be a procedure from the vacuum group about changing valves. Is there anything I missed?

Also, there is an approved procedure in DocuShare that is not included on the WCD, Calibrating Network Analyzer PLACLN-PR-NA-CAL. Just wanted to point that out for if the WCD is updated in the near future

Megan
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20240520/72910056/attachment.html>


More information about the Pansophy mailing list