Yes, I believe we could, the SRF-PR-ACC-NEG-PREP-R1 Procedure is what we use for the CapaciTorr HV 200 ( Insitu Accelerator Enclosure),  CapaciTorr HV 200  are also Activated 2X using the L2HE-PR-CLNRM-NEG-PREP-R2 Procedure

________________________________
From: Allen Samuels <samuels at jlab.org>
Sent: Friday, May 16, 2025 11:05 AM
To: Gregory Marble <marble at jlab.org>; Adam Grabowski <adamg at jlab.org>; John Fischer <fischer at jlab.org>; Tony Reilly <areilly at jlab.org>; Matt Weaks <weaksmc at jlab.org>
Cc: pansophy <pansophy at jlab.org>
Subject: NEXTorr/NEG pump Procedures

Good morning, all,

Pansophy was working on updating a C75 Activation of C75 FPC waveguide NEXTorr pump procedure for use in ER5C when it was noticed that there are several other projects that have NEG ion pump prep procedures as well; chiefly SRFOPS-PR-ACC-NEG-PREP-R1<https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-289328/SRFOPS-PR-ACC-NEG-PREP-R1.pdf> and L2HE-PR-CLNRM-NEG-PREP-R2<https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-278565/L2HE-PR-CLNRM-NEG-PREP-R2.pdf>. We were wondering if these procedures could be combined into a master procedure that could service multiple projects. As the owners of these documents and the project coordinators, would you be able to provide any insight? I've included the draft ER5C procedure for comparison.

Thank you for your time,

Allen
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/pansophy/attachments/20250516/604a5b45/attachment.htm>


More information about the Pansophy mailing list