<p>Hello GCIOVATI <br>
Your request has been completed. <br><br><br>
Request Type: General Request <BR/>
Request ID: 305 <BR/>
Priority Level: 1 <BR/>
Request Notes: The cavity status board only shows one annealing for 5C75-RI-023: but the cavity went through another annealing on 21oct2022 see ER5C-FURN-CAV-HEAT #36. Could you please update the cavity status board accordingly? Thanks,Gigi
<BR/>
Date Completed: 2023-10-19 12:02:09<BR>
Completed By: BOOKWALT<BR/>
Completion Notes: THE CAV_STATUS_BRD IS LOOKING FOR SPECIFIC DATES TO BE FILLED IN WHICH IS WHAT IS DISPLAYED ON THE STATUS BOARD. FOR THE ER5C-FURN-CAV-HEAT TRAVELERS THAT VARIABLE IS SHOWN ON THE SECOND ROW OF THE TABLE AS DATETIMECOMPLETE. THIS HAD NO DATA AND THEREFORE WAS NOT FOUND BY THE QUERY. IF ANOTHER DATE FIELD IS PREFERRED FOR THIS COLUMN PLEASE LET US KNOW USING THE SERVICE REQUEST SYSTEM. THANK YOU
<br><br><br>
Have a great day. <br>
Pansophy Team</p>