Hi Mike-PD,<br>
<br>
I show below our shrinking list of tasks needing an injector access
to complete the PEPPo installation. If there is an access
(controlled or restricted) lasting at least 1 hour then something
useful can be done. Tasks listed in yellow are done by EGG &
PEPPo. If DC power has one body available then EES could complete
hookup of 6 more trim magnets. I'd coordinate, prioritize parallel
tasks during the access.<br>
<br>
If acceptable then once you decide all we need to know is the day
(Thursday or Friday) and start time (to enter injector).<br>
Someone from PEPPo will be at the 3pm RECO meeting in MCC to learn
the decision.<br>
<br>
Thanks,<br>
Joe<br>