Dear PEPPo Collaborator,<br>
<br>
The home stretch...remember to hydrate!<br>
<br>
Our final readiness review is April 20th.&nbsp; This review will include a
status update on our 7 subsystems (vacuum, magnets, annihilation, fiber
array, compton, hardware, online analysis) and address the 9 issues
raised by the initial readiness review (see punchlist ATLIS #12134).&nbsp;
Eric and I will make the presentation, you should of course attend if
possible.<br>
<br>
The outcome of this review and the sign-off by the laboratory is a
requirement to perform the experiment.<br>
<br>
You have two deadlines.<br>
<br>
<b>#1. Wed April 11th</b> - Documentation and procedures are required.&nbsp;
At the Shift Takers wiki link you should upload documentation (source
&amp; printable PDF) and then at the "How To" link you should deposit
succinct instructions to accomplish various tasks.&nbsp; It is important the
outline/skeleton of documentation and procedures exists, even if the
actual material (or updated versions) arrive later.&nbsp; It is fairly
obvious where you "own" some piece of the experiment that you are
responsible to contribute information.&nbsp;&nbsp; I suggest adding dates and
versions to your documents.&nbsp; The wiki link:
<a class="moz-txt-link-freetext" href="https://positron.jlab.org/wiki/index.php/Shift_Takers_Online_Documentation_and_Procedures">https://positron.jlab.org/wiki/index.php/Shift_Takers_Online_Documentation_and_Procedures</a><br>
<br>
<b>#2. Mon April 16th</b> - Updates one at most two slides describing
status of your system should be e-mailed to Eric and myself to help
collect a coherent picture of the experiment readiness.&nbsp; Implicit in
this list is documentation and "how-to".&nbsp; List tasks you seem
accomplishing before and/or w/ beam by 4/18 and tasks that you would
schedule during the beam off week of 4/18-4/24 in advance of the
experiment.<br>
<br>
I've put a list below w/ your initials; augment what I've missed:<br>
<br>
All vacuum - JG<br>
PEPPo viewers, bpm, FC - JG<br>
PEPPo collimators - AF<br>
PEPPo magnets - JG/SG<br>
Beam - momentum setup w/ cryounit + 5 MeV dipole spectrometer YK/AF/JG<br>
Beam - final optics for T1 and T2 targets - YK/AF/JG<br>
Model G4 PEPPo mechanical &amp; magnetic layout- PG<br>
Model G4 Beamline mechanical &amp; magnetic layout - SG<br>
Model Elegant Beamline mechanical &amp; magnetic layout - YK<br>
Detector - annihilation counters, analysis macro - TF/SS<br>
Detector - fiber array counters, on-line analysis - PG/LA<br>
Compton polarimeter detector - EV/EF<br>
Compton analyzing magnet - EV/MB<br>
Compton AP simulation - EV/LA/OD<br>
DAQ hardware config - EV/EF/RS/AC/JSR<br>
DAQ readout/decode - EF/RS/JSR/AC<br>
DAQ xscaler - BM/RS<br>
DAQ analysis macro position differences - JSR<br>
DAQ analysis macro charge asymmetries- RS<br>
DAQ analysis macro Compton experimental asymmetries - EF/JSR<br>
<br>
What else?<br>