<div class="moz-text-html" lang="x-western"> <b>Daily RC Report 5/24:</b><br>
Source calibration of the Compton and Annihilation detectors proceeded
successfully yesterday.&nbsp; This morning the final 2B alignment of PEPPo
beam line was completed.&nbsp; The preliminary report is that all elements
are in very good alignment, generally meaning better than ~0.1mm in X,
Y.&nbsp; We'll get a preliminary survey transmittal ASAP and final
thereafter; if certain values are needed immediately please let me
know.&nbsp; Gross design values can be taken from drawings on wiki and
as-founds w/ handy tape measure in the interim.&nbsp; This afternoon
annihilation detector checkout continued and majority of beam line lead
shielding (1/8" sheet and lead shot) have been placed.&nbsp; As of now
Operations the INJ/NL are in beam permit and injector elements needed
for PEPPo are being turned on.&nbsp; We'll collect a punchlist of repair
items which will likely be addressed following the Friday 8am meeting.&nbsp;
Beyond repairs please bring to my attention any tasks in tunnel, ISB,
DAQ not captured below.<br>
<br>
<b>Noteworthy items:</b><br>
1. We're at the precipice of the PEPPo experiment - good luck to
everyone!<br>
2. Before Friday 7am move shielding/materials you want access to
upstream of injector gate, for quicker access.<br>
3. Daily RC meeting is 3:30pm in MCC control room.&nbsp; If you have
something to show tomorrow post it here:<br>
<a class="moz-txt-link-freetext" href="https://positron.jlab.org/wiki/index.php/Fri%2C_May_25%2C_2012_%28Grames%29">https://positron.jlab.org/wiki/index.php/Fri%2C_May_25%2C_2012_%28Grames%29</a><br>
<br>
<b>Next 24 hours:</b><br>
<blockquote><u>Thursday, 5/24 - SWING</u><br>
  <ul>
    <li>INJ/NL in Beam Permit for HCO until ~1900</li>
    <li>Cs &amp; Co source calibration of Compton NaI detectors</li>
    <li>Mount annihilation counters w/ more shielding on beam line</li>
    <li>Complete cabling of fiber array detector</li>
    <li>Add shielding house for future TS1 (trigger) and E1 (energy)
scintillator detectors<br>
    </li>
  </ul>
  <u>Friday, 5/25 - OWL</u><br>
  <ul>
    <li>No planned work</li>
  </ul>
  <u>Friday, 5/25 - DAY (SHIFT LEADER = Matt Poelker)</u><br>
  <ul>
    <li>INJ/NL will be locked up ~early<br>
    </li>
    <li>Anticipate ~2 hours of INJ controlled access for repairs,
followed by beam recover to FC2<br>
    </li>
    <li>Complete Task CB03 - recover beam to FC2, setup longitudinal
polarization, checkout new viewer ITV5D03, solenoid MPT5D04 and
collimator current monitoring w/ beam ISCxxx.<br>
    </li>
    <li>Complete Task CB11 - Calibrate BCM0L02 against FC2, setup BCM
receiver gain and FSD thresholds</li>
    <li>Calibrate T2 (electrometer) &amp; PEPCUP (picoammeter) against
one another and FC1<br>
    </li>
  </ul>
  <u>Friday, 5/25 - SWING (SHIFT LEADER = Arne Freyberger)</u><br>
  <ul>
    <li>Complete Task CB06 - Study 0L orbit vs QS-quad, QJ-quad,
MBV-dipole, cryounit gradient to learn good "straight-ahead orbit"</li>
    <li>Complete Task CB05 - Perform quad centering of 0L01, 0L02,
0L02A, 0L03, 0L03A, 5D00, 5D01</li>
  </ul>
</blockquote>
<br>
</div>