Dear PEPPo Collaborator,<br>
<br>
It will likely never be said that the logistics and scheduling
process for PEPPo was a no-brainer. With that in mind it is timely
to update and summarize the remainder of the run period as foreseen:<br>
<br>
1. Beginning Monday, June 11th and lasting until the end of the run
the following will apply:<br>
<br>
<u>Weekdays (M-F):<br>
</u>
<ul>
<li>0000-0600: OWL PEPPo shift; however beam terminates at 6am,
shift crew may leave</li>
<li>0600-1500: Injector will be Restricted Access; PPE is closed
toe shoes, long pants, long sleeves</li>
<li>1500-1600: Operations will restore Injector/NL to Beam Permit</li>
<li>1530 : Daily RC meeting will continue as usual in MCC<br>
</li>
<li>1600-2400: SWING PEPPo shift</li>
</ul>
<u>Weekends (S-S):<br>
</u>
<ul>
<li>0000-0800: OWL PEPPo shift</li>
<li>0800-1600: DAY PEPPo shift</li>
<li>1600-2400: SWING PEPPo shift</li>
</ul>
2. The last two days of the PEPPo run period is being allocated to
Beam Studies. Consequently, the PEPPo run is presently scheduled to
end on Wednesday, June 27th at 0800. In this case, the remaining
shifts through Friday, June 30th will be cancelled however those
already signed up will receive shift credit.<br>
<br>
3. Considering the unusual scheduling it is worthwhile to consider
the following, as of today:<br>
<ul>
<li>By heart-beats, we are 44% (14.5 days / 33 days) complete</li>
<li>By viable shifts, we are 54% (43.5 shifts / 80.75 shifts)
complete</li>
</ul>
<p>4. The PEPPo end of run party will be Thursday, June 28; details
TBD<br>
</p>