    <p><b>Daily RC Report</b>
    </p>
    <pre>Yesterday swing, we continued data taking at 5.5 MeV/c. Early this morning, there was a vacuum spike in 
PEPPo beam-line. Joe and Matt leak checked the beam-line but did not find any leaks - might have been a virtual
leak. We were down for 12 hours. During the Injector access, more lead shielding was added to the left side of
the Spectrometer. Now we are back taking data, this time at 200 nA instead of 100 nA due to the background 
rate reduction with the new shielding.
</pre>
    <p>Next 24 hours:
    </p>
    <p>Sunday, 6/10 - SWING SL=Eric Voutier
    </p>
    <pre>   production at 5.5 MeV/c.
</pre>
    <p>Monday, 6/11 - OWL SL=Erica Fanchini
    </p>
    <pre>   production at 5.5 MeV/c - Beam stops at 6:00 am.
</pre>
    <p>Monday, 6/11 - DAY, No Beam - Restricted Access.
    </p>
    <p>Monday, 6/11 - SWING SL=Mike McCaughan </p>
    <pre>   background runs and  production at 5.5 MeV/c.

</pre>