[Poltarg12] No meeting today
Christopher Keith
ckeith at jlab.org
Thu Oct 15 09:49:07 EDT 2020
Hello everyone,
I apologize for the extremely late notification, but you had probably
guessed it anyway. There will not be a meeting today. We'll have a
meeting four weeks from now.
Here's an exhaustive update about the target:
*_NMR:_*
James Maxwell is assembling the latest version of the NMR Q-meter,
designed by himself and Hai Dong. James has also completed his overhaul
of the NMR software controls. The newest version completely replaces
LabView w/ James' homebrewed Python code. I've seen screenshots, and it
looks pretty good. We'll try both of these during the next cool-down.
*_Target Cart:_*
The support frame for the target cryostat has been fabricated and
mounted to the electronics cart in the EEL. It needs to be painted and
aligned. Dave Griffith is installing all the electronics cables on the
cart now and running them through a retractable cable tray attached to
the cart. The tray will track with the cryostat as it rolls over the
cart, keeping the cables and some some small vacuum hoses neatly in place.
*_Cryostat:_***
James Brock and Casey Flanagan disassembled the cryostat for
modifications for the next cool-down. We'll add a small tube inside the
refrigerator that should give us a more accurate measurement of the
vapor pressure over the liquid helium bath. This is needed for accurate
calibration of the NMR signal. Mark Hoegerl will weld attachment points
on the back of the cryostat for hanging it from the above-mentioned
support frame. James Brock is doing a major overhaul of the NMR &
microwave insert. This will include a new microwave horn/reflector on
the underside of the bath. He and I did some simple measurements on a
variety of different horn shapes last week. They do a nice job of
distributing microwave power over the 2 cm width of a target sample, but
not quite its full 4 cm length. James will have some new designs 3D
printed soon.
*_Installation:_*
We still seem to be on Hall B's unofficial schedule for 2022. When
asked, I told Stepan Stepanyan that two months would be required to
install and get the target fully functional in Hall B. James Brock and
myself met with Hall B's engineer and designer, Bob Miller and Cyril
Wiggins, to discuss the installation. Bob agreed to move the 500 liter
buffer dewar of liquid helium from its current location to the same
level as the target cryostat. This will permit us to use a shorter and
more efficient transfer line to the target refrigerator. Bob will
design and construct a small platform with handrails so we can access
the cryostat for loading and unloading ammonia samples while the target
is inside the central detector. Cyril will design a support frame for
the downstream raster magnet that attaches to the same rails on the
target electronics cart as the cryostat. Finally, we discussed the
location of the vacuum valve and thin window between the cryostat and
beam line.
*_Cool-down:_*
We are on track for a cool in late November. Its primary focus will be
DNP of butanol and deuterated butanol samples and loading and unloading
same with the latest version of James Brock's retraction mechanism.
James Maxwell has been preparing the samples.
I think that's about all. Let me know if you have any questions.
Best regards,
Chris
--
______________________________________________________
Christopher D. Keith, PhD
Jefferson Lab, Suite 6 email: ckeith at jlab.org
12000 Jefferson Ave. ph: 757-269-5878
Newport News VA 23606 fax: 757-269-5235
______________________________________________________
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/poltarg12/attachments/20201015/9e4dd105/attachment.html>
More information about the Poltarg12
mailing list