I like the proposal. I will comment at ITAC that setting the machine up for 1 GeV beam to Hall C will take one day if this experiment is run exclusively (no other halls) and five days if other experiments are scheduled to run in parallel. Upper bound three calendar weeks if exclusive. Jay