[Primexd] RC week summary, March 6-13
Alexander Austregesilo
aaustreg at jlab.org
Thu Mar 21 14:44:05 EDT 2019
Dear Collaborators,
I started my duty as run coordinator when the energy of the accelerator
was reduced from 11.6 to 11.2 GeV for stability reasons. During this
down time, Chris Keith and Chris Carlin finalized the settings for the
liquid He target operation and left the operation to the shift crew.
Beam restoration was expected during owl shift on Friday, we therefore
staffed the counting house from midnight on and started filling the lHe
target. The entire day was dedicated to beam restoration, including ion
chamber calibration, radiation level checks and several iterations of
harp scans. We had to abandon the plans to perform an active collimator
scan on Friday evening after the beam position was very unstable and the
beam was finally taken away to perform a spin dance. In parallel, the
CDC HV was ramped to nominal values. It was confirmed that the currents
in the inner rings of the CDC did not reach critical values for nominal
beam conditions. Around 8pm, we started to take production data on the
lHe target, 200 nA beam current, 5 mm collimator and a 10^-4 Al
radiator. During the whole weekend, we saw the y position of the beam on
both 5C11B and the active collimator drift by several hundred mum, even
though it was locked on the AC. During the swing shift on Saturday,
Sasha performed trigger studies and included the CDC into the read-out.
Unfortunately, a bug in the reconstruction algorithm for straight tracks
stopped the monitoring system, so the group decided to exclude the CDC
for the rest of the weekend. On Monday morning, this problem was fixed
and the CDC could be included into the data stream. After a rapid access
to reset the communication to the ComCal HV main frame, the beam
position was stable enough to perform a scan of the active collimator,
which resulted in a about 10% higher transmission at the new nominal
position (-0.1, 0.0). For the rest of my tenure, the conditions for
production data taking were extremely stable. Out of the 91.5h of CW
beam on target, we could use 87.2h (95%) and recorded almost 8 billion
triggers.
(from
https://halldweb.jlab.org/wiki/index.php/Run_Coordinator_report:_spring_2019_w7)
My sincere thanks go out to all shift crews and experts on-call during
this week.
Alex
More information about the Primexd
mailing list