Colleagues,<br>
Omar has agreed to assist me with RECO this start-up. The majority of
his
focus will be on I&amp;C systems but he will also be addressing some
other EES areas as needed. <br>
<br>
At Steve's maintenance meeting on Monday we agreed to the following HCO
schedule:<br>
<br>
<u><b>August 7th</b></u><br>
Begin getting into the HCO frame of mind. Be thinking about what you
need to do to meet the schedule. <br>
<br>
<u><b>August 10th - 14th</b></u><br>
Perform HCO w/o beam on accelerator systems. Report status of HCO to
Lauze/Garza. This can be done via phone or e-mail but the preferred
method is to make a log entry with<font color="#000000"> </font><font
 color="#000000"><i>HCO
Complete</i> </font>somewhere in the title. <font color="#000000">Due
to the cryomodule installation at 1L04, the North Linac will be in
Restricted Access during the Day shift. This will require some DC Power
and RF HCO to be conducted on Swing or Owl Shift. Please plan
accordingly. <u><b>See Steve's calendar, and attend RECO meetings, for
up-to-date details on tunnel lock-up status.</b><br>
</u><br>
</font><u><b>August 11th - 18th (excluding the 15th and 16th)</b></u><br>
RECO meetings start. Meetings will be held in the MCC conference room
from 1530-1600.<br>
<br>
<u><b>August 14th -16th</b></u><br>
Starting on Swing Shift Friday (if we are ready) Operations will
perform HCO with beam by restoring 5 pass 5.9 GeV from an allsave made
at the end
of the last run. Operations will be instructed to call for support for
show
stoppers only, all other problems will be documented and addressed on
Monday August
17th. <br>
Once 5.9 GeV is established they will scale down to the run energy of
5.764GeV.<font color="#3366ff"><br>
</font><br>
<u><b>August 17th - 18th</b></u><br>
Monday Day Shift is tentatively reserved to make repairs of the items
identified during the weekend restoration. During these two days we
need to perform HCO w/o beam of all Hall systems.<br>
<br>
<u><b>August 19th</b></u><br>
<i>ALL systems must be ready for beam to all three Halls<br>
<br>
</i>Thanks, Ron<i><br>