Dear Nick,
in the run 4903 the RICH PMT 297 for some reason is missing, we have no 
signal there.
Therefore, to have good time calibration of the whole system, I would 
ask to cook run 4973, where that PMT is back on.
Thank you,
Marco



Il 2020-05-09 22:16 Nikolay Markov ha scritto:
> Dear all,
>  run 4903 is cooked
>  /volatile/clas12/rg-a/production/pass0/v1_1.1.34/calib/train/
> 
>  Nick.