[Rgc] [New Logentry] RC Daily Summary July 6, 2022
bueltman at jlab.org
bueltman at jlab.org
Wed Jul 6 08:00:02 EDT 2022
Logentry Text:
--
Data taking throughout the day, evening and night with semi-stable beam at 4.0 nA.
During the day, HV mainframe hard reboot fixed the ECAL HV board (sector 5). Will need to be investigated during maintenance day.
During evening shift, reduced beam raster radius (Vpp from 2.2 V to 2.1 V).
Raffaella installed new mon12 version in counting house. Beam is not touching bottom of target cell anymore.
Changed HWP from OUT to IN.
Beam stopped at 7:30 for Maintenance Day
Plan:
Maintenance Day started at 7:30
- Injector (horizontal Wien magnet PS) and North Linac RF work
- Will need to do Moller run when beam returns, most likely evening shift
Polarized target work (change to deuteron material)
We will have a RC meeting today at 12 PM.
RC Meeting Coordinates:
https://jlab-org.zoomgov.com/j/1608674253?pwd=SFZyYmZLWXJieGtpV2dEdVRiUE...
Meeting ID: 160 867 4253
Passcode: 786506
Data taking progress:
Day 4.0 nA on NH3 (HWP OUT), runs 16250 (9 M), 16251 (15 M), 16252 (18 M), 16253 (47 M)
Swing 4.0 nA on NH3 (HWP OUT), runs 16254 (1 M), 16256 (63 M)
and (HWP IN), runs 16257 (66 M)
Owl 4.0 nA on NH3 (HWP IN), runs 16259 (58 M), 16260 (35 M)
Accumulated on NH3 (last seven days):
HWP OUT 202 M events (Pt pos)
HWP IN 206 M events (Pt pos)
HWP IN 448 M events (Pt neg)
HWP OUT 372 M events (Pt neg)
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4011633
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/rgc/attachments/20220706/01cae663/attachment.html>
More information about the Rgc
mailing list